Pile Drilling and Pile Installation (Belectric Gulf)
- Project name: Drilling, Concreting & Pile Installation - South Amman PV plant
- Project owner: Belectric Gulf.
- Drilling Contractor: SUMER
- Location: Jordan- South Amman
- Scope of work:
1.1 Surveying works
Using qualified Surveyor and with accepted tolerances using calibrated surveying instrument, location shall be marked after receiving AutoCAD drawings shows the final Pile location, and consequently.
1.2 Drilling works
Upon Belectric confirmation for the surveying points, SUMER shall proceed with the piling works using the Rope. SUMER will drill holes with diameter of 25 cm and depth 1.3 meter, and required to build and install concrete steel pile at the project site. The total quantities of works procured will be defined during the construction by the Contractor.
continue reading
Related Posts
This scope of work outlines the procedures and objectives for conducting a site visit to assess the current condition of drilled water wells.
Groundwater Resource Assessment of the Disi Aquifer in Southern and Central Jordan was carried out for water producing wells and piezometer wells.
At SUMER, our ERT survey identifies aquifers and depth accurately. Findings guide us in designing optimal well construction plans for efficient water extraction.